Bond Project Timeline

Bond 2023 Project Timeline

During the Crowley ISD School Board meeting on Jan. 11, 2024, trustees received updates on many of the voter-approved projects included in the Bond 2023 package. These new schools, security enhancements and renovations across the district are scheduled to be completed over the next four years with no tax rate increase.

Tentative Bond Project Timeline:

2024

  • New Elementary School No. 16 Opens (funded by 2007 bond)
  • Security Fencing for Elementary Playgrounds
  • Roof Replacement at H.F. Stevens Middle School
  • District-wide facility, safety and security improvements

2025

  • New Elementary School No. 17 Opens
  • District-wide facility, safety and security improvements

2026

  • New Track & Field Complex Opens (phase 1)
  • Expansions/Renovations:
    • Deer Creek Elementary
    • Meadowcreek Elementary
    • Sycamore Elementary
    • Crowley Ninth Grade
    • North Crowley Ninth Grade
    • North Crowley High School
  • District-wide facility, safety and security improvements

2027

  • New Crowley High School Opens
  • New Middle School No. 5 Opens
  • Inclusive Outdoor Learning Center (partnership with the city of Crowley)
  • Indoor Track Opens
  • District-wide facility, safety and security improvements